Monday	6/2/2008
Install 20" water line thru Santa Clara Intersection. Continue on Catch Basin decks and local depressions. Remove median and center pole at st.18+50 on Central Ave
Tuesday 6/3/2008
Install 20" water line thru Santa Clara Intersection. Continue on Catch Basin decks and local depressions.
Wednesday 6/3/2008
Install 20" water line thru Santa Clara Intersection. Continue on Catch Basin decks and local depressions.
Thursday 6/4/2008
Install 20" water line thru Santa Clara Intersection. Place base and prepare to pave. Continue on Catch Basin decks and local depressions.
Friday 6/5/2008
Install 20" water line thru Santa Clara Intersection. Pave trench and re-open Santa Clara Intersection. Continue on Catch Basin decks and local depressions.
Monday 6/9/2008
Starting at st 18+00, south of the median on Central, excavate and install 60" Storm Drain. Central Ave will continue to be closed from Hwy 126 to Santa Clara St.
Tuesday	6/10/2008
Continue to excavate and install 60" storm drain.
Wednesday 6/11/2008
Continue to excavate and install 60" storm drain.
Thursday 6/12/2008
Continue to excavate and install 60" storm drain. Form new footing for center pole at median.
Friday	6/13/2008
Continue to excavate and install 60" storm drain. Pour footing for center pole at median.