Fillmore High Athletic Complex Rises
The Fillmore High School new Athletic Complex is coming along nicely. Last week crews poured concrete for the gym floor and completed backfilling of the stormwater capture system. Above are some of the crews working away to get the project completed. The anticipated completion date is February 2027.
The Fillmore High School new Athletic Complex is coming along nicely. Last week crews poured concrete for the gym floor and completed backfilling of the stormwater capture system. Above are some of the crews working away to get the project completed. The anticipated completion date is February 2027.

Fillmore Unified School District Assistant Superintendent of Business Services Denise Berrington said, “Last week at the Fillmore High School Athletic Complex, crews poured the concrete for the gym floor and completed backfilling of the stormwater capture system. Temporary work platforms are being installed to allow crews to safely continue building the concrete block walls and prepare for the next concrete pour. This work helps support the structure as construction moves upward.
With deep underground utility work nearing completion, foundation and concrete slab work for the Lobby, Restrooms, Locker Rooms, Wrestling Rooms, Athletic Training Rooms, and Coaches’ Offices is scheduled to begin next week.
The anticipated construction completion date for the project is February 2027. We look forward to sharing continued progress as this exciting project takes shape!”