|
Fillmore High Athletic Complex Construction Update
![]() Fillmore High School’s new Athletic Complex has been busy under construction, with multiple crews moving in and out daily. Above is an aerial view of the site with the old gym in the bottom left, and the Flashes football field at top right. By Gazette Staff Writers — Thursday, January 29th, 2026
![]() Above is the Athletic Complex surrounded by vertical scaffolding, with masonry/grouting work taking place on the 16-foot walls. The FHS Athletic Complex project’s anticipated completion date is February 2026. ![]() Crews have competed trenching for footings and caisson layout. ![]() Above is a view of the main stadium and site looking towards the old gym. ![]() Above are crews welding the embeds at grid line 8 at the corners of the gym. Construction continues to make steady progress at the Fillmore High School Athletic Complex, with multiple trades actively working on structural, electrical, plumbing, and site development components. Masonry crews advanced vertical construction, completing scaffold work and grouting masonry walls up to approximately 16 feet in height. Structural embeds were welded at key grid line locations, supporting the ongoing buildout of the gym and surrounding athletic facilities. |





