Veterans Memorial receives facelift
Veterans Memorial Building.
Veterans Memorial Building.

Story courtesy Annette Cardona, Community Services Supervisor.

The Memorial Building bathroom construction started April 27, 2009 and the estimated completion day will be
September 4, 2009. Both bathrooms were gutted out to the concrete on the floor, the plumbing and electrical have
both been replaced, a wall was knocked out extending the men’s bathroom all the way to the dinning room, the entry door to the women’s restroom was moved over about two feet, and the front entry doors have been moved and replaced.

Also, the entry way was changed to make it handicap accessible with a ramp, and the wall outside the women’s restroom was redone, the boards with dry rot were replaced, the hole on the outside wall has been dry walled and
the wall will be repainted. All the toilets, partitions, sinks, and light fixtures will all be brand new along with all the other bathroom necessities needed.

The Fillmore-Piru Veterans Memorial Building Bathroom Project is paid for by RDA monies and CDBG MONIES. The cost of the project will be $207,220.69 without any additional change orders for the project.