Pacific Coast Pipeline Fillmore Site Update on 2012 Field Activities

August 2012 — It’s been a busy summer for Chevron at the former Pacific Coast Pipeline property (67 E. Telegraph Road), where we are continuing site clean-up, overseen and inspected by the US Environmental Protection Agency (EPA), State of California, and Ventura County.

Water spraying, wind monitoring, air sampling, and other measures are used to minimize and control dust as we work. We appreciate community interest in the five site tours hosted this year by the EPA and Chevron and we hope to schedule additional tours before year-end. Watch our website for updates and information: www.fillmoreworks.com

We are on schedule to meet the following milestones by mid-October:

• 32 concrete foundations removed

• 8,000 tons of concrete crushed and recycled

• 11 miles of pipeline excavated and removed

Learn more at: www.FillmoreWorks.com