City Water Well No. 10 Project Still Underway
Back in January of this year the City of Fillmore announced the Water Well No. 10 Project drilling and construction of a new groundwater well was to begin at Delores Day Park, with a three-phase project with crews working into the late nights. Above is the worksite for the project. The playground is temporarily closed for removal and replacement of playground chips, and the area designated for drilling Well No. 10 is fenced off. Restrooms and park shelters remain open and accessible. Photo credit Gazette staff.
Back in January of this year the City of Fillmore announced the Water Well No. 10 Project drilling and construction of a new groundwater well was to begin at Delores Day Park, with a three-phase project with crews working into the late nights. Above is the worksite for the project. The playground is temporarily closed for removal and replacement of playground chips, and the area designated for drilling Well No. 10 is fenced off. Restrooms and park shelters remain open and accessible. Photo credit Gazette staff.

Posted on January 21, 2026, courtesy https://www.fillmoreca.gov/m/newsflash/Home/Detail/259
What is Well No. 10 Project?
The Water Well No. 10 project replaces abandoned Well No. 5 that is located at Delores Day Park.
The project consists of three phases:
1. Exploratory drilling to determine viable water supply and quality.
2. Building around the wellhead, access driveway, generator and communication enclosure. Landscaping might be included in this phase.
3. Equip well with piping, electrical, and mechanical components.
For more information on Well No. 10 Project, visit our page dedicated Well No. 10 landing page visit https://www.fillmoreca.gov/1351/Water-Well-No-10-Project.
Below is the Well No. 10 Landing Page:
Project Update 1/28/26
The project will involve drilling and construction of a new groundwater well at Delores Day Park, 868 Goodenough Rd, Fillmore, CA.
Potential Impacts and Mitigation
While minimal noise and activity are expected, crews will be doing everything possible to minimize disruption to the surrounding neighborhood. Traffic Control Measures and sound barriers will be in place to reduce impact.
Project Schedule (Times and Dates are subject to change based on contractor negotiations)
Dates & Activity
Jan 12 - Jan 16: Installation of temporary fence & shoulder closure (7am - 5pm)
Jan 26 - Feb 4: Soundwall Installation
Feb 6 - Feb 20 : Pilot Hole Drilling (24/7 Operation)
Mar 9 - Mar 23: Well Expansion Drilling (24/7 Operation)
Mar 23 - Apr 27: Well Development (7am - 5pm) 7- days a week
Apr 27 - May 8: Well # 5 Destruction (7am-5pm) 7 - days a week
Will Delores Day Park be open during the Well No. Project?
The playground at Delores Day Park is temporarily closed for removal and replacement of playground chips, and the area designated for drilling Well No. 10 is fenced off. Restrooms and park shelters remain open and accessible.
Questions?
For questions related to Project Well No. 10, contact Public Works at 805-535-6625 or visit https://www.fillmoreca.gov/1351/Water-Well-No-10-Project.